2.1a. Modul Handbook of B.Eng Civil Engineering

 

Modul name

Integrated Design and Construction

Level module

6 (undergraduate)

Abbreviation of applicable

SIP 620427

Sub-heading, if applicable

 

Courses included in the module, if applicable

 

Semester

VII

Person in charge

Ir. Amril Maruf Siregar, S.T., M.T

Lecturer

Ir. Amril Maruf Siregar, S.T., M.T

Language

Bahasa Indonesia, English

Classifications within the curriculum

Compulsory/ elective course

Teaching (hours per week during the semester

2 class hour lecture (2´170 minutes lecture) ´ 16 weeks

Workload per semester

340 minutes lecture is divided into 100 minutes face to face interaction, 120 minutes structural activities, 120 minutes independent study

Credit points

2 SKS (3.12 ECTS)

Learning objective

A01

Fulfilling task with moral, ethics and manner (2-S)

A02

Capable to be part of team work and showing social awareness (4a-W)

A03

Being eager to be independent (4b-S)

C04

Capable to design and apply innovative construction, eco-friendly, low-cost, adaptive to climate change (7a-S)

P05

Mastering tools and software, collecting information, and applicable procedure that has been determined (7b-S)

C06

Capable to fulfill task as technician, analyst, and engineer with low-cost approach, emphasizing in coastal building and infrastructure that adaptive to climate change (8-S)

C07

Knowledgeable and skillful to fulfill the requirements of applicable standard incorporating factual and specific expertise emphasizing in coastal building and infrastructure that adaptive to climate change; hence having competencies to complete task properly and thoroughly (9-S)

A08

Responsible and enable to fulfill task holistically (10-S)

A09

Have a willingness to learn throughout lifetime (11-S)

Note: C: cognitive; A: affective; P: psychomotor

Course Learning Outcomes/ Competencies

Being able to:

1.      Mention the differences between manufacturing and service industries, and construction industry (C1;2)

2.      Elaborate the definition of integrated (C1;2)

3.      Mention the advantages of integration (C1;2)

4.      Explain the structure of a construction team, construction project management team, consortium approach, construction team roles, responsibilities and skills (C2;2)

5.      Explain the structure, client team roles, responsibilities and skills within the integrated design construction process (C2;2)

6.      Explain the project insurance terms and conditions (C2;2)

7.      Explain the project payment system (C2;2)

8.      Characterize each payment system, the benefits and risks that may occur (C4;6)

9.      Explain the model trade agreement, model terms and conditions (C2;2)

10.  Explain the information and communication technology (ICT) (C2;2)

Content

A.      Lecturing

1.      Construction legal entity: construction team structure, construction project management team, consortium approach, construction team roles, responsibilities and skills

2.      Client team – structures, responsibilities and skills: structure, client team roles, responsibilities and skills within the integrated design construction process

3.      Project insurance conditions

4.      Project payment system: project bank accounts

5.      Trade agreement model, terms and conditions model

6.      Information and communication technology (ICT):

7.      Project management ICT, summary of other ICT tools available for IDCsr practitioners

B.      Practical work

 

Study/ exam achievement

Assessment Aspect (%)

A1

A2

A3

C4

P5

C6

C7

A8

A9

Quiz (20%) - writing test

Ö

 

Ö

 

Ö

 

 

Ö

 

Mid test (25%)- writing test

Ö

 

Ö

 

Ö

 

 

Ö

 

Final test (35%)- writing test

Ö

 

Ö

 

Ö

 

 

Ö

Ö

Final Task (20%)

Ö

Ö

Ö

Ö

Ö

Ö

Ö

Ö

Ö

Score index

A

A ³76

B+

71 £ B+ < 76

B

66 £ B < 71

C+

61 £ C+< 66

C

56 £ C < 61

D

50 £ D < 56

E

E < 50

 

Forms of media

Software

Hardware

Ms. Office (PPT, Ms Word, Ms. Excel)

Projector

 

LCD

 

Laptop, computer